Diatom mud construction steps diatom mud construction precautions

The decoration materials are constantly updated, and we have not heard of many things. I don’t know how to choose when I choose the decoration materials. Diatom mud is one of them. After we purchase, we don't know how to apply diatom mud. Today, Xiaobian will take a look at the diatom mud construction steps and diatom mud construction precautions! I hope that I am purchasing the decoration. Material for you.


硅藻泥施工步骤


Diatom mud construction steps


1. Ensure that the base surface is flat, compact and clean, the water content is less than 10%, the PH value is less than 10, and the yin and yang angles and lines are straight and straight;


2. In the paint professional and technical personnel, formulate the diatomite formula according to the on-site climatic conditions, add the clean water in proportion to the raw materials according to the method provided by the company, and stir on the site for a certain time to allow the mixture to fully dissolve and react completely;


3, carefully cover the parts that are not sprayed, check the base surface conditions to meet the specified requirements before construction, pay attention to ensure timely adjustment of construction speed, to ensure that the outer wall wet film thickness of 3mm, dry film 2mm; inner wall wet film thickness of 1.2mm, Dry film 0.9mm;


4. The coating rate should be around 0.8-1.0m2/kg.


5. Firstly prepare clean water according to the construction amount, add 90% of the construction water to the mixing vessel, then pour it into the dry powder of Kangli diatom mud, soak it and stir it with electric mixer for about 20 minutes, stir and add another 10%. Clean water and mix well before use. The product after mixing with water is best used on the same day.


6. The diatom mud is applied twice, and the first pass (about 1.5 mm thick) is about 50 minutes after completion (according to the on-site climate conditions, the surface is not sticky, and the bottom is covered with material) .



Diatom mud construction precautions


1. For the empty drum or the cracked substrate, it must be pre-treated, and the base is brushed twice after the cleaning.


2. Avoid strong winds and direct sunlight during the construction process, and it is suitable for natural drying.


3. The diatom mud product is a water-soluble veneer material and cannot be used in places directly exposed to water.


4. Physical properties of natural raw materials, including certain differences in their color, are normal phenomena and do not affect product quality.



硅藻泥施工步骤


5, diatom mud should not be used in the environment below 5 °C. Do not eat diatom mud to avoid getting into the eyes.


6. Keep safe storage distance with children and strengthen labor protection when using.


7. Protect the existing finished products before construction, and protect the materials outside the construction surface with health materials.


8. For the hollow or cracked substrate, pre-treat the substrate, if necessary, apply the oil to the substrate or pre-scrape the coating.


9. Add clean water strictly according to the specified ratio, and mix well with electric mixer.


10. Avoid direct sunlight exposure during construction.


For us to decorate the decoration materials is the most important, and diatom mud is our good choice! The above is the diatom mud construction steps and diatom mud construction notes introduced by Xiaobian today. For more information, please stay tuned to the renovation home.


Bobcat Hydraulic Parts

The test bench was developed for Main Pump and motor of Bobcat Hydraulic pump truck, excavator, and rotary drill.
The test range, the test items and the test requirements are consistent with the JB/T7039-7044 and other relevant industry standards.
JUHENG can supply all kinds of Bobcat Excavator Parts like Bobcat Hydraulic Pump Spare Parts, etc,Bobcat Concrete Machinery Parts,Bobcat Excavator parts,
Bobcat Crane parts,Bobcat Pile Machinery parts,Bobcat Road construction machinery parts,Bobcat Port Machinery Parts, etc.such as pump walking motor rotary motor assembly and parts boom and arm cylinders seal repair kits all kinds of filter bucket bucket tooth and all Undercarriage Parts and so on.
Hydraulic Piston Pump, Duplex Pump, Short-Stroke Pump, Noise/Vibration Reduction, High Self-Priming Ability, Rotational Stability, High Efficiency, High Pressure, Compact Size, Reduction of Overall Length.

We export GENUINE PUMP, OEM PUMP, Bobcat Hydraulic Main Pump,Bobcat Main Hydraulic Pump,Bobcat Hydraulic Pump,Bobcat Hydraulic Pump Spare Parts, AFTERMARKET PUMP. We are specialized in OEM PUMP & AFTERMARKET PUMP. We export 95 NATIONS. Please contact us If you need STABLE SUPPLIER.

Bobcat Hydraulic Main Pump,Bobcat Main Hydraulic Pump,Bobcat Hydraulic Pump,Bobcat Hydraulic Pump Spare Parts,Bobcat Hydraulic Main Pump Assembly,Bobcat Main Pump,Bobcat Pump,Bobcat Hydraulic Parts,Bobcat Excavator Parts

Jining Juheng Hydraulic Machinery Co., Ltd. , https://www.jhexcavator.com

Posted on